Construction is underway on the next phase of the Paseo Santa Fe Street Improvement Project. Crews will begin at Oceanview Drive and work toward Civic Center Drive.

If you are driving North you will not be able to turn left on to Guajome St. This is the last time you will see traffic on the west side of Santa Fe unit 2020

Sewer mains will be constructed first, then storm drain facilities and water lines, followed by the undergrounding of overhead utility lines

Surface improvements such as landscaping, sidewalks, and lighting will be completed during the final segment.
South Santa Fe Avenue

•Traffic control will be installed and will extend from Oceanview Drive to just south of Terrace Drive.

•The traffic control will shift traffic to the east on the S. Santa Fe Avenue, while maintaining two-way traffic.

•Work will take place along the west side of the street. Parking will be restricted in this area.

•Access to entry ways will be maintained.

The construction is expected to be completed in March, 2020.

The City will strive to minimize traffic impacts sometimes associated with construction. The City and its contractors thank the public in advance for their patience as the City works to improve the downtown core.

http://www.cityofvista.com/home

NC Daily Star Staff
NC Daily Star Staffhttps://NCDAILYSTAR.COM
Terry Woods has been a North County resident for over three decades. Community activist, Board of Directors Vista Chamber of Commerce, Member Carlsbad Chamber Commerce Married to Kathy Woods for 47 years, three children, three grandchildren and five grand dogs.
RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Recent Comments